Tiles Fixing Guideline
|
The surface to
be paved to be flat, and free from substance: Dust,
impermeable products, soluble salts, and all those
products which are incompatible with adhesive material.
In case of crumbling of the base, it must be removed
till getting firm surface. |
|
|
Prior
To Installation |
|
Spending on the
surface using a dentate trowel, whose size will very
from 6x6mm. to 9x9mm. depending on the size and manufacturer’s
instructions. |
|
|
Laying |
|
Hit the tile with
a rubber hammer (from the center to the edges of the
tiles). In order to distribute and level the tile. |
|
|
Leveling |
|
Tiles must be paved
leaving a gap between them which will vary from 1
mm. To 3 mm. Joint for placing them |
|
|
Spacing |
|
Joining has to
be carried out using a rubber palette knife, which
will be used to compress material with backwards and
forwards movements. In this way. Joint will be field
to over-flowing. Anyhow please follow the manufacturer’s
introduction in how to use the product-drying time,
removing leftovers, and cleaning. |
|
|
Joining |
|
Once the
work has been finished. There are leftovers of the
employed materials which have to be removed as soon
as possible (cement, joints material, ets…). For this,
we recommended using a cement remover of any other
acid based descaling product. |